WSP : Construction Progress Report from Water System and Public Latrine [February 04, 2022]
Today is February 04, 2022, the increase in the construction of the water system and public latrine per day is 60% where the focus of work carried out by workers is currently on wall work items. The brickwork and plastering of the walls have been completed, and at this time workers have also completed more than half of the ceramic work on the walls.
In addition to wall work with the type of ceramic installation work, other workers have also filled the floor area and for the roof as I said in the previous post, this work is done separately because the roof used in this construction is a light steel frame type.
All types of work that have been and are being carried out by workers in the construction of the water system and public lantrine are in accordance with technical analysis regarding the work and the progress of the construction is 60%. To be clearer, steemit users as donors of this project can look at the type of work table and the current condition table of the construction as below.
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | Complete |
4. | Column | Complete |
5. | Beam | Complete |
6. | Wall | Almost complete |
7. | Floor | Almost complete |
8. | Water tub | Almost complete |
9. | Roof | Almost complete |
10. | Painting | On Progress |
11. | Electrical | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View | |
Back View | |
Back and Right View | |
Back and Left View |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Related Links
WSP : Construction Progress Report from Water System and Public Latrine [January 31, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 29, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 25, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 22, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 19, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 15, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 11, 2022]
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien
Thanks
@klen.civil
This post has been featured in the latest edition of Steem News...
Thanks
I have included this post in the 35th issue of Steem News Magazine For Steemit Platform | February 05, 2022.
Amazing dear. It is now almost done
This is a good progress and i am glad, we have gotten to this point. Thank you very much for sharing the update.
@tipu curate
Upvoted 👌 (Mana: 5/6) Get profit votes with @tipU :)
Прекрасно! Люблю, когда всё постепенно и продвигаетесь к заверению своей цели!
Thanks
Sebentar lagi bakanlan selesai ya.. semangat buat team yg bekerja👍