WSP : Construction Progress Report from Water System and Public Latrine [February 04, 2022]

in STEEM FOR BETTERLIFE3 years ago
Note: 50% of Rewards to accelerate the construction of the Water System and Public Latrine @worldsmile account

image.png

Construction Progress Report from Water System and Public Latrine

Today is February 04, 2022, the increase in the construction of the water system and public latrine per day is 60% where the focus of work carried out by workers is currently on wall work items. The brickwork and plastering of the walls have been completed, and at this time workers have also completed more than half of the ceramic work on the walls.

In addition to wall work with the type of ceramic installation work, other workers have also filled the floor area and for the roof as I said in the previous post, this work is done separately because the roof used in this construction is a light steel frame type.

All types of work that have been and are being carried out by workers in the construction of the water system and public lantrine are in accordance with technical analysis regarding the work and the progress of the construction is 60%. To be clearer, steemit users as donors of this project can look at the type of work table and the current condition table of the construction as below.

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingComplete
3.SloofComplete
4.ColumnComplete
5.BeamComplete
6.WallAlmost complete
7.FloorAlmost complete
8.Water tubAlmost complete
9.RoofAlmost complete
10.PaintingOn Progress
11.ElectricalOn Progress
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front Viewimage.png
Front and Right Viewimage.png
Front and Left Viewimage.png
Right Viewimage.png
Left Viewimage.png
Back Viewimage.png
Back and Right Viewimage.png
Back and Left Viewimage.png

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Related Links


Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

I have included this post in the 35th issue of Steem News Magazine For Steemit Platform | February 05, 2022.

 3 years ago 

Amazing dear. It is now almost done

 3 years ago 

This is a good progress and i am glad, we have gotten to this point. Thank you very much for sharing the update.

 3 years ago 

Прекрасно! Люблю, когда всё постепенно и продвигаетесь к заверению своей цели!

 3 years ago 

Thanks

 3 years ago 

Sebentar lagi bakanlan selesai ya.. semangat buat team yg bekerja👍

Coin Marketplace

STEEM 0.23
TRX 0.28
JST 0.042
BTC 104956.85
ETH 3880.98
SBD 3.32