World Smile Project : Construction of Free Education Center - Update November 04, 2021
The construction of the Free Education Center has now experienced a very significant progress movement where the two main heavy works, namely the installation of roofs and walls, have now experienced a 90% progress increase. Apart from other work that has been completed, namely Pole or Column, Lower Beam, Floor Adhesive, Floor, Top Beam and Trestle, the stages of work that must be carried out after the two main works of roof and wall installation reach 100% are electrical installation work, ceiling installation , stairs and painting.
The target for the completion of the roof installation only takes less than one working day, while for the complete wall installation, the workers need about one to two working days. For the movement of progress, after I did an analysis of the overall construction technique of the free education center development, it can be set at 70%.
Below I also attach in a table form about the 12 main jobs that have been, are being and have been completed by the workers with the code Complete which means it has been completed perfectly, Almost Complete which means being done and almost finished, and On Progress is the work to be done in the near future and the material inventory is already on site.
Apart from the table I explained, I also attach photos of the progress achieved as of today for the public to consume for the sake of transparency of the World Smile Project program.
Number | Type of work | Notes |
---|---|---|
1 | Pole or Column | Complete |
2 | Lower Beam | Complete |
3 | Floor Adhesive | Complete |
4 | Floor | Complete |
5 | Wall | Almost Complete |
6 | Top Beam | Complete |
7 | Trestle | Complete |
8 | Roof | Almost Complete |
9 | Stairs | On Progress |
10 | Ceiling | On Progress |
11 | Electrical installation | On Progress |
12 | Painting | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View | |
Inside view | |
Inside view |
Project Name | Free Education Center |
---|---|
Beneficiary | Khairul Huda School Boarding |
Address | Syamtalira Aron, North Aceh - Indonesia |
Related Links
World Smile Project : Construction of Free Education Center - Update November 01, 2021
World Smile Project : Construction of Free Education Center - Update October 26, 2021
World Smile Project : Construction of Free Education Center - Update October 24, 2021
World Smile Project : Construction of Free Education Center - Update October 20, 2021
Note:
- Update Construction Progress with Complete Percentage Values can be seen in @sofian88's post (Free Education Center)
- Completely update budget expenditure can be seen in @miftahuddin's post (Free Education Center)
- Total Budget Revenue and Expenditure from the World Smile Project is handled by @heriadi and @irawandedy
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve
Thanks
@klen.civil
remarkable progress in the construction of the study hall of the world smile project which looks almost complete.
#club5050
#worldsmileproject50pc
We will try to finish construction by the end of the month at the latest
the performance shown by the world smile project team is very good in completing its development target,, good luck always
#club5050
#worldsmileproject50pc
Thanks a lot
Terimakasih updatenya.
#club5050
#worldsmileproject50pc
ur welcome
@tipu curate
Upvoted 👌 (Mana: 3/6) Get profit votes with @tipU :)
Very good report
#club5050
#welovepowerups
Thanks sir
very nice project.I like this innovation. And I wish for success.
Thanks
You are welcome Sir.