World Smile Project : Construction of Free Education Center - Update November 04, 2021

in STEEM FOR BETTERLIFE3 years ago
Note: 50% of payout is donated to charity via @worldsmile account

image.png

World Smile Project : Construction of Free Education Center

The construction of the Free Education Center has now experienced a very significant progress movement where the two main heavy works, namely the installation of roofs and walls, have now experienced a 90% progress increase. Apart from other work that has been completed, namely Pole or Column, Lower Beam, Floor Adhesive, Floor, Top Beam and Trestle, the stages of work that must be carried out after the two main works of roof and wall installation reach 100% are electrical installation work, ceiling installation , stairs and painting.

The target for the completion of the roof installation only takes less than one working day, while for the complete wall installation, the workers need about one to two working days. For the movement of progress, after I did an analysis of the overall construction technique of the free education center development, it can be set at 70%.

Below I also attach in a table form about the 12 main jobs that have been, are being and have been completed by the workers with the code Complete which means it has been completed perfectly, Almost Complete which means being done and almost finished, and On Progress is the work to be done in the near future and the material inventory is already on site.

Apart from the table I explained, I also attach photos of the progress achieved as of today for the public to consume for the sake of transparency of the World Smile Project program.

Table of the main types of work from the construction of the Free Education Center
NumberType of workNotes
1Pole or ColumnComplete
2Lower BeamComplete
3Floor AdhesiveComplete
4FloorComplete
5WallAlmost Complete
6Top BeamComplete
7TrestleComplete
8RoofAlmost Complete
9StairsOn Progress
10CeilingOn Progress
11Electrical installationOn Progress
12PaintingOn Progress
Design of the Free Education Center Construction

Progress of Free Education Center Development As of November 04, 2021
PerspectivePresent Condiition
Front Viewimage.png
Front and Right Viewimage.png
Front and Left Viewimage.png
Right Viewimage.png
Left Viewimage.png
Inside viewimage.png
Inside viewimage.png
Another photo related to the execution of the work
image.pngimage.png
image.pngimage.png
MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameFree Education Center
BeneficiaryKhairul Huda School Boarding
AddressSyamtalira Aron, North Aceh - Indonesia

Related Links


Note:


  • Update Construction Progress with Complete Percentage Values ​​can be seen in @sofian88's post (Free Education Center)
  • Completely update budget expenditure can be seen in @miftahuddin's post (Free Education Center)
  • Total Budget Revenue and Expenditure from the World Smile Project is handled by @heriadi and @irawandedy
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @steemcurator01 @steemcurator02 @pennsif @el-nailul @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

remarkable progress in the construction of the study hall of the world smile project which looks almost complete.

#club5050
#worldsmileproject50pc

 3 years ago 

We will try to finish construction by the end of the month at the latest

 3 years ago 

the performance shown by the world smile project team is very good in completing its development target,, good luck always

#club5050
#worldsmileproject50pc

 3 years ago 

Thanks a lot

 3 years ago 

Terimakasih updatenya.

#club5050
#worldsmileproject50pc

 3 years ago 

ur welcome

 3 years ago 

Very good report

#club5050
#welovepowerups

 3 years ago 

Thanks sir

 3 years ago 

very nice project.I like this innovation. And I wish for success.

 3 years ago 

Thanks

 3 years ago 

You are welcome Sir.

Coin Marketplace

STEEM 0.17
TRX 0.12
JST 0.027
BTC 55499.23
ETH 2917.22
USDT 1.00
SBD 2.30