Official Report WSP : Contruction Progress of Free Education Center East Aceh 90% [October 04, 2022]

in STEEM FOR BETTERLIFE2 years ago
image.png

Leaving 10% of the total weight of the Free Education Center construction for East Aceh which means 90% of the construction of this building has been completed with various main work items such as Site Clearing and Landing Altitude Measurement, Footing, Sloof, Post, Beam, and Steel Truss Roof. So, the 6 main items of the work are currently set to have been completed perfectly and have a weight of 72%. Two other items being worked on at the moment are the Round Floor Building with a weight of 5% from 8% and Wall with a weight of 13% from 15%. As well as other items that are still waiting to be completed, the two items currently being worked on as I said above are painting or finishing items with a weight of 0% from 5%.

In total, of the 9 main items that have been worked on, are being worked on and have not been done, the determination of the construction weight is 90%. For all information, at this time the main focus of work is done on waal items, namely in the form of plastering work which is expected to be completed in the next 1 to 2 days, and of course, floor work items are also in progress marked by compaction of the soil that will be used for casting the floor. The target for completion of this floor item ranges from 1 to 3 working days ahead. And of course the installation of doors and windows is also an additional item that only takes a maximum of 1 working day.

The target for completion of this construction is expected to be completed in the next 1 to 2 weeks, I have conveyed this to the workers to speed up the work. This is the construction report from the Free Education Center for East Aceh this week after I did a technical analysis of the supervision of this building, and of course below I also attach a table of the percentage of the main work items from this building along with documentation in the form of photos for donors to see. world smile project.

NoType of WorkPersentase
1.Site Clearing and Landing Altitude Measurement5/5
2.Footing10/10
3.Sloof10/10
4.Round Floor Building5/8
5.Post15/15
6.Wall13/15
7.Beam12/12
8.Steel Truss Roof20/20
9.Painting0/5
Total Persentase90/100

And below I also attach several documents in the form of photos of the work carried out today, as follows :

Current condition of Free Education Center Development for East Aceh
image.pngimage.png
Front ViewBack View
image.pngimage.png
Right ViewLeft View
image.pngimage.png
Another perspectiveAnother perspective
image.pngimage.png
Another perspectiveAnother perspective
image.pngimage.png
Main roomTeacher's room

This is the progress report on the construction of the free education center for East Aceh which has started today as of October 04, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.

Free Education Center Building Information for East Aceh (World Smile Project INT)
ProjectFree Education Center
TypeBuiding Contruction
Size or Dimention9 x 6 meter
AddressTanjong Punti village, Madat district, East Aceh
Benefit recipientsEarly Childhood
Teacher@steemitcountry

Cc : @pennsif @el-nailul @heriadi @irawandedy @mariana4ve @ubongudofot @patjewell @alanasteemit @hungry-griffin @rme


East Aceh, October 04, 2022
@klen.civil
WSP Construction Supervisor

Sort:  

Hello friend!
I'm @steem.history, who is steem witness.
Thank you for witnessvoting for me.
image.png
please click it!
image.png
(Go to https://steemit.com/~witnesses and type fbslo at the bottom of the page)

 2 years ago 

Really you have done a lot of good and beneficial work for poor children. Hope your work will be completed very soon.

 2 years ago 

Thanks

 2 years ago 

the extraordinary project that you did with the world smile project team, with hard work and high team spirit made a charity project 90% completed and hopefully it will continue until it is 100% complete ,, good luck always for the world smile project team ,,,,

 2 years ago 

Thanks

 2 years ago 

Wow! The finish line is in sight!
Well done! 👏🏻👏🏻

 2 years ago 

Thanks

 2 years ago 

Ve preparando la sonrisa @klen.civil proque ya la construcción está casi lista, espero ver la foto con esa gran sonrisa al momento de la inauguración-

 2 years ago 

Thanks

 2 years ago 

I hope this program is useful for the world of education which is not fully touched by programs from the government.

 2 years ago 

Aamiin

This post has been featured in the latest edition of Steem News...

Coin Marketplace

STEEM 0.21
TRX 0.20
JST 0.033
BTC 92268.82
ETH 3102.93
USDT 1.00
SBD 3.03