Official Report WSP : Contruction Progress of Free Education Center East Aceh 45% [September 6, 2022]

in STEEM FOR BETTERLIFE2 years ago
image.png

Moving from where I live in North Aceh district to East Aceh district with a distance of about 2 hours drive whose purpose is to carry out routine supervision of the Free Education Center construction that is being worked on there, of course on Tuesday as of September 6, 2022, I am very happy to see the progress this construction. Where the work items have shown very significant progress.

Site Clearing and Landing Altitude Measurement, Footing, Sloof, and Post have been completed thanks to the solution I took to increase the workforce a few days ago. Of the four works, according to technical analysis, construction progress has shown 40%, while other work items in the form of Round Floor Building have started work and currently have achieved progress of 2% from 8% while Wall work items have also been carried out simultaneously and have progress of 3% of the total 12%.

To note with the calculation of the percentage of the Round Floor Building work items calculated from the pile under the floor and 15% casting for the floor, while the wall work items are calculated from laying bricks for one teacher's room, then for the outside area which is only 45 cm high and in the area spear screen for the building. The wall calculation will end when the plastering is finished.

So in total the construction progress of the free education center for East Aceh as of September 6, 2022, after I did a construction engineering analysis, it can be stated that it has progressed at 45% of the total work items, and to be clearer, the world smile project donors can see the table below this below.

NoType of WorkPersentase
1.Site Clearing and Landing Altitude Measurement5/5
2.Footing10/10
3.Sloof10/10
4.Round Floor Building2/8
5.Post15/15
6.Wall3/12
7.Beam0/10
8.Steel Truss Roof0/20
9.Painting0/5
10.Finishing0/5
Total Persentase45/100

And below I also attach several documents in the form of photos of the work carried out today, as follows :

Current condition of Free Education Center Development for East Aceh
image.pngimage.png
Front ViewBack View
image.pngimage.png
Right ViewLeft View
image.pngimage.png
Another perspectiveAnother perspective
image.pngimage.png
Another perspectiveAnother perspective
Other documentation is in the form of photos of workers in activity and on site materials
image.pngimage.png
Soil hoarding for floorsEarthworker for floor

This is the progress report on the construction of the free education center for East Aceh which has started today as of September 6, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.

East Aceh, September 6, 2022
@klen.civil
WSP Construction Supervisor

Sort:  
 2 years ago 

Thank you for the report on the construction of the free education building, I hope it can be realized as soon as possible, so that we can focus on other projects in Nigeria and South Africa

 2 years ago 

With my pleasure

 2 years ago 

Qué bonito es ver como la obra se eleva y va tomando forma.

Los niños deben estar muy alegres al ver el proceso de construcción. Saludos y bendiciones a todos .

 2 years ago 

Thanks
😇

 2 years ago 

45% es un porcentaje fabuloso, y ver los ladrillos es emocionante. Admiro tu dedicación @klen.civil, viajar dos horas para ver como va la escuela es de admirar, sobre todo cuando todos tenemos otras ocupaciones.

Me emociona pensar en la foto de inauguración, espero tengas una gran sonrisa ese día.

 2 years ago 

Thank you
😇

 2 years ago 

Nearly 50%!
Thank you for keeping us informed week after week! ☕

 2 years ago 

Pleasure
😇

This post has been featured in the latest edition of Steem News...

Coin Marketplace

STEEM 0.21
TRX 0.20
JST 0.034
BTC 98085.38
ETH 3350.61
USDT 1.00
SBD 3.03