Update the Financial Realization Report of the Steem.Amal Housing Project Phase X 98%
Dear steemian
In order to maintain transparency and accountability, I as a field officer in charge of steem.amal's homework would like to convey the use of funds during the laying of the first stone to date.
Today I have spent as much as Rp. 63,611,000,- for the purpose of buying C excavated materials and manufacturing materials or the equivalent of 670 SBD at today's market price.
If we accumulate with a percent of all budgeted costs as much as Rp. 65,000,000,-. So the current expenditure is around 98% of the total cost.
The following is an attachment to the table that I recapitulated from the first use of the funds sent by the @el-nailul program manager.
Here I attach it in the form of an excel table;
We still have a lot of money to spend in order to achieve the targets that have been planned. The support of all parties to help steem.amal is what we really hope for. And all forms of disbursement of funds sourced from steem charity cash will be published at least 2 times a week in order to maintain the level of transparency and accountability.
For previous fund realization reports, you can directly access the following posting link:
Update the Financial Realization Report of the Steem.Amal Housing Project Phase IX 95%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase VIII 90%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase VII 56%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase VI 54%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase V 40%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase IV 34%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase III 29%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase II 26%
Update the Financial Realization Report of the Steem.Amal Housing Project Phase I 23%
Note
I will update the financial realization report at least once a week according to the conditions in the field
Estimated material costs will fluctuate according to market prices
MAIN INFORMATION FROM STEEM AMAL HOUSING PROJECT
Project Name | Steem Amal Housing Project |
---|---|
Budget | Rp. Rp 65,000,000 |
Beneficiary | Mr. Samsul |
Address | Nibong, Syamtalira Bayu-North Aceh, Indonesia |
We are proud of all involved for the success of the steem.amal housing program. Thank you to all who have supported the course of this program for the sake of humanizing humans with a decent place to live in.
For the physical progress of the steem.amal housing, friends can immediately see the post @klen.civil