Calculation #1 (labor and material needs) 🏠

in #engineering7 years ago (edited)
Greetings, how are you steemit friends? Glad to see you again and hopefully keep the spirit. Today I will discuss about the application of the labor and material needs I have previously discussed and I will exemplify to the building we are planning.

In the previous discussion we have discussed about the needs of labor and materials on the work of excavation, backfill, foundation, walls, reinforced concrete work and other work.

In accordance with the picture below then we will calculate the needs of labor and materials needed.



credit @kharrazi


credit @kharrazi


credit @kharrazi


credit @kharrazi


credit @kharrazi


credit @kharrazi


credit @kharrazi


credit @kharrazi


The work we will count is

  • Soil excavation work [1] [2]

The form of excavation is carried out in accordance with the one shown in the drawing, If at the place of excavation found pipe disposal or wires that are still working then you should immediately notify the authorized agency to get further instructions.

  • Backfill work [2]

Backfill work is done with upcoming ground, backfill done several layers, then each layer is compacted with compactor and others, to produce maximum density and no decrease of floor.

Backfill work under the floor is done after excavation work foundation soil is completed

'- Stone pairs [3]

Stone used comes from rivers or mountains with shapes and sizes corresponding to the cross section to be worked on, the stone must be clean of mud and other organic substances that can damage the structure.

  • Mountain rock foundation [3]

Mountain rock used in this work must be really hard, strong, clean, free of cracks and should come from reliable sources of retrieval. Prior to installation, the stone must be moistened with water between three and four hours before use in such a way that each stone is fully exposed to water.

  • Reinforced concrete work [4]

Slab dim. 15/20 cm
The reinforced steel that has been produced must match the drawing of the plan.
Installation of previously manufactured formwork must be appropriate to the size of the slab and the side-support pair as a binder. Installation should be straight and strong so as not to melt at the time of casting. The casting in accordance with the proportion of the mixture.

Column (Practical column) dim. 13x13 cm [5]

The making of marks on the basis should be precise on the axles specified in accordance with the plan.
The reinforcement and brace columns must match the image. Installation of special formwork on double-sided practical columns (formerly formwork oiled) and reinforced with reinforcing wood on column sides.

  • Wall work [6]

Bricks are soaked for a few minutes in water to prevent the cement from being absorbed by the bricks so that the adhesion will decrease.
Preparing the mounting position on the column to position the masonry correctly and in accordance with the drawing plan.

  • And Plastering [7]

QUESTION


In accordance with the picture above, how much labor and materials needed to complete the works?


ANSWER


I use technical analysis in accordance with Indonesian National Standard to complete the calculation of labor and material requirements. [8]

  • Soil excavation

Is known.

InformationAmount
Length x width x height16.00 x 0.70 x 0.70
Amount7,840 m3

Coefficient of 1m3 excavation of soil.

InformationAmount
Workers0.750 Person per day
Overseer0.025 Person per day

Amount as needed

ItemsInformationAmount
Workers0.750 Person per day x 7,840 m35,880 Person
Overseer0.025 Person per day x 7,840 m30.196 Person
  • Backfill work

Volume a (backfill foundation work)
Is known.

InformationAmount
1/3 backfill7,840 / 3
Amount2,613 m3

1m3 backfill coefficient a

InformationAmount
Workers0.750 Person per day
Overseer0.025 Person per day

Amount as needed

ItemsInformationAmount
Workers0.750 Person per day x 2,613 m31,960 Person
Overseer0.025 Person per day x 2,613 m30.065 Person

Volume b
Is known.

InformationAmount
Length x width x height3.85 x 3.85 x 0.10
Amount1,482 m3

1m3 backfill coefficient

InformationAmount
Workers0.300 Person per day
Overseer0.010 Person per day
Soil1,200 M3

Amount as needed

ItemsInformationAmount
Workers0.300 Person per day x 1,483 m30.445 Person
Overseer0.010 Person per day x 1,483 m30.015 Person
Soil1,200 x 1,483 m31,779 m3
  • Sandfill work

Volume Sandfill work
Is known

InformationAmount
Length x width x height3.85 x 3.85 x 0.05
Amount0.741 m3

Coefficient of 1m3 sandfill work.

InformationAmount
Workers0.300 Person per day
Overseer0.010 Person per day
Sand1,200 M3

Amount as needed

ItemsInformationAmount
Workers0.300 Person per day x 0.741 m30.222 Person
Overseer0.010 Person per day x 0.741 m30.007 Person
Sand1,200 x 0.741 m30.887
  • Works stone pairs

Volume stone pairs work
Is known.

InformationAmount
Length x width x height16.00 x 0.70 x 0.10
Amount1,120 m3

Coefficient of 1m3 stone pairs is required.

InformationAmount
Workers0.780 Person per day
Stonemason0.390 Person per day
Foreman0.039 Person per day
Overseer0.044 Person per day
Mountain rock1,200 m3
Sand0.432 m3

Amount as needed.

ItemsInformationAmount
Workers0.780 Person per day x 1,120 m30.874 Person
Stonemason0.390 Person per day x 1,120 m30.437 Person
Foreman0.039 Person per day x 1,120 m30.044 Person
Overseer0.044 Person per day x 1,120 m30.044 Person
Mountain rock1,200 m3 x 1,120 m31,344 Person
Sand0.432 x 1,120 m30.484 Person
  • Mountain rock foundation work

Volume Mountain rock foundation work

InformationAmount
Average width(0.25 + 0.60) / 2 = 0.425 m
Length x width x height16.00x0,425x0,60
Amount4,080 m3

Coefficient 1m3 Mountain rock foundation

InformationAmount
Workers1,500 Person per day
Stonemason0.750 Person per day
Foreman0.075 Person per day
Overseer0.075 Person per day
Mountain rock1,200 m3
Portland cement163,000 Kg
Sand pairs0,520 m3

Amount as needed.

ItemsInformationAmount
Workers1,500 Person per day x 4,080 m36,120 Person
Stonemason0.750 Person per day x 4,080 m33,060 Person
Foreman0.075 Person per day x 4,080 m30.306 Person
Overseer0.075 Person per day x 4,080 m30.306 Person
Mountain rock1,200 m3 x 4,080 m34,896 m3
Portland cement163,000 Kg x 4,080 m3665,040 Kg
Sand pairs0.520 m3 x 4,080 m32,122 m3

CONCLUSION


At this first stage calculation we have completed the calculation

  • Soil excavation
  • Backfill work
  • Mountain rock fondation

In accordance with the work and working drawings above then the needs of labor and materials for this stage is.

ItemsAmount
Workers15,501 Person
Stonemason3,497 Person
Foreman0.350 Person
Overseer0.633 Person
Soil1,779 m3
Sand1,373 m3
Mountain rock6,240 m3
Portland cement665,040 Kg
Sand pairs2,122 m3

to be continued ...

This calculation is just an example and can be used by anyone, this calculation is in accordance with technical analysis of Indonesian National Standart.[8]

Thanks to friends who have visited this blog and to scientists who are willing to sacrifice their time to realize a better civilization.

This is all I can write on this occasion, for all the mistakes and lack of writing as a servant of God, I apologize.


source:

[1] www.wikipedia.org

[2] www.wikipedia.org

[3] www.wikipedia.org

[4] www.wikipedia.org

[5] www.wikipedia.org

[6] www.wikipedia.org

[7] www.wikipedia.org

[8] www.hdesignideas.com


Do you love science? by respecting the work of others and not plagiarism then you are welcome to join steemstem by using @science tags or @SteemSTEM tags, you can also chat with us in steemit chat/steemstem channel.


Best regards @kharrazi

Sort:  

thank you my brother has given a very good knowledge and hard to get.
by calculating work materials and labor,
whether we also need to calculate the target how many days are ready to be done ? @ kharrazi

yes, we also have to calculate the day needed in work, because in addition to time cost becomes the determinant of work success.
thank you for stopping @fulsketch :)

thank you brother for sharing your experience
hopefully can be useful for me :)

Coin Marketplace

STEEM 0.16
TRX 0.17
JST 0.029
BTC 69432.76
ETH 2492.61
USDT 1.00
SBD 2.53