Today I am going to open a quick contest about calculating labor requirements on excavation work manually.

This contest can be followed by anyone and the contest is open to the public.

Each participant is welcome to provide answers with appropriate calculations.

The right and fastest answer will be rewarded

10 SBD

After the announcement of the winner.

There is only one winner.

CLUE


Ok, here's the drawing job.


( @kharrazi credit )


( @kharrazi credit )


( @kharrazi credit )


( @kharrazi credit )

QUESTION?


In accordance with the above picture then how much labor needs at the job of excavation manually?

RULE


  • You answered in the comments in this post.
  • Answers should be accompanied by engineering calculations.
  • You can resteem this post as proof you care for the community.
  • The correct and fastest answer will be chosen.
  • There is only one winner.

I will rate each answer and choose the winner.

TIME


The contest ends on October 3rd 2017, at 18.00 (UTC + 7).


You can check my previous posts to find out how to calculate labor and material requirements in accordance with technical analysis.

Happy counting friends ๐Ÿ˜‰


This contest I especially created to make people more interested in calculating their own work needs, this contest has no relationship with any community/party.

Steem on!


Best regards @kharrazi

Sort: ย 
Loading...

Question: In accordance with the above picture then how much labor needs at the job of excavation manually?

My Answer: A lot

XD

ย 7 years agoย (edited)

thanks for joining this contest @trumpman
hahahaha.... XD

I tried my best XD

yup, I know.
I really appreciate your hard work buddy XD

ka jaya sagoe nyan.....

Loading...

3.7m x 5m x 0.6m=11.1cubics
We need to know how many cubics, a person can dig manually.
If we guess that a person can dig 0.3cubics per hour
A person will need 37 hours of work (11.1/0.3=37)
or
37 persons for one hour of work.

to find out how many workers to complete 1 cubic of axavation, you can see my previous post @nikoleondas ;)

ย 7 years agoย (edited)

Your contest is good, but my answer is not there, because I am not an expert in the field of development. thank you @kharrazi, keep your spirit in the field of development.

ย 7 years agoย (edited)

thank you, but you don't need expert in this field, because I have explained it in my previous post so you just need to read it :P

Thanks for what?

DetaiLLLLLLL

This post was resteemed by @resteembot!
Good Luck!


Curious? Check out:


The @resteembot users are a small but growing community.
Check out the other resteemed posts in resteembot's feed.
Some of them are truly great.

Thanks for sharing @kharrazi .

This post was resteemed by @resteembot!
Good Luck!


Curious? Check out:


The @resteembot users are a small but growing community.
Check out the other resteemed posts in resteembot's feed.
Some of them are truly great.

Coin Marketplace

STEEM 0.18
TRX 0.16
JST 0.029
BTC 75902.83
ETH 2895.60
USDT 1.00
SBD 2.58